Izmir · 2023
Irrigation pumps and cold-store compressors peak in different months. Land-based PV is the main path to scale when roof area is insufficient for facility-level need.
Energy site layout was planned while protecting production land. The EPC line was coordinated with irrigation infrastructure and the seasonal operating calendar.
The operation runs irrigation, cold storage and processing loads across a seasonal calendar. Roof area alone could not carry the capacity target, and land use had to stay compatible with ongoing agricultural activity.
The objective was to define an energy site with clear boundaries, connection path and EPC delivery that respects both the seasonal load profile and field operations.
Size land-based capacity against irrigation and cold-chain consumption patterns.
Protect productive land and define clear energy-site boundaries in the layout.
Deliver EPC in coordination with irrigation infrastructure and seasonal windows.
From land and connection analysis through ground-mount EPC and commissioning — structured for an agricultural operating environment.
Land & connection analysis
Transformer distance, grid connection path and land-use balance clarified before layout finalisation.
Ground-mount engineering
Structure design, module layout and cable routing planned around field access and irrigation lines.
Field EPC delivery
Construction, module install and cabling under one coordination line with seasonal scheduling.
Commissioning & reference
Acceptance testing and seasonal performance reference defined at handover.
Layout decisions started from land boundaries and connection feasibility — not from maximum module density. Irrigation routes and field access were mapped before structure placement.
EPC delivery was sequenced around agricultural activity windows. Commissioning established a seasonal reference point for operations, without fixed generation guarantees.

Feasibility & land survey
Load profile, land boundaries and connection capacity documented together.
Layout & engineering
Ground-mount design, cable routing and protection coordinated with irrigation infrastructure.
Field EPC delivery
Structure install, module mounting and cabling completed under one project line.
Commissioning & handover
Acceptance testing, seasonal reference definition and operations documentation delivered.
The showcase outcome is a commissioned land-based line with clear site boundaries and a documented connection path — giving the operation a visible energy asset without claiming fixed economic returns.
Field delivery was coordinated with the seasonal calendar. Irrigation infrastructure and access routes remained intact in the final layout.
Showcase scenario — performance and economic outputs are illustrative only; not a commitment or guarantee.Energy boundaries set apart from production land
Grid link and transformer route documented at handover
Performance baseline aligned to irrigation calendar
Irrigation lines and access routes preserved in layout
Land-based PV layout with clear boundaries from production areas.
Share your irrigation and cold-store need — we will outline capacity against your seasonal profile.

Share your facility type, target capacity and delivery expectations — we will outline a feasibility frame similar to these showcases.